Projects - Head of Signalling & Telecommunications  
Name Hj. Yahya Hj. Akob
Age 41 years
Educational University of Technology Malaysia, Kuala Lumpur
Experience
1983 - 1989

Signalling & Communication Inspector, KTMB Gemas

  • Responsible for planning and maintenance of signalling & communicatioin equipment and installations from Tampin - Lapis.
  • Involved in KTMB projects for rehabilitation of track between Gemas - Tampin (1984 - 1985) and Gemas - Paloh (1987 - 1988)
Jan 90 - Dec 90

Signalling & Communication Inspector, KTMB Johor Bahru

  • Responsible for planning and maintenance of signalling and communication equipment from Renggam - Tg. Pagar (Singapore)
  • Involved in KTMB project for rehabilitation of track between Paloh - Bukit Timah
Jan 91 - Mar 93

Technical Executive, KTMB Special Project (Head Quarter)

  • Project co-ordinator for re-signalling project for provision of New Route Relay Interlocking (RRI) for Paloh and Layang-Layang Stations.
Apr 93 - June 95

Technical Executive, KTMB Double Tracking Projects (Division of Signalling and Communications)

  • Responsible for co-ordination and inerfacing of all railway engineering works comprising of civil, track, signalling, communication and electrification works.
  • Responsible for testing and commissioning of signalling and communication equipment :
    a) Centralised Traffic Control (CTC)
    b) Automatic Train Protectioin System (ATP)
    c) Fiber Optic Network
    d) Signal Post Telephone Network
    e) Mobile Train Radio Network
    f) Station Interlocking Systems
    g) Automatic Reversible Block System
Jul 96 - June 97

Technical Executive, KTMB for Centralised Train Control System (CTC).

  • Responsible for testing and commissioning of CTC System.
  • Responsible for maintenance of CTC and all communication system under KTMB Double Tracking Project :-
    a) Fiber Optic Network
    b) Signal Post Telephone Network
    c) Mobile Train Radio Network
    d) PABX Network
Jul 97 - June 00

Construction Manager, TIME Salam Engineering S/B.

  • Responsible for coordination overall planning and implementation of the following projects :-
    a) Kuala Lumpur Central - Phase 0
    b) Extension of stabling lines at Rawang and Port Klang and the construction of EMU Depot at Seremban
    c) Rail Link Project to West Port
    d) Segamat Inland Port
General Manager | Projects - Head of Signalling & Telecommunications | Projects - Signalling Engineer | Projects - Telecommunication Engineer | Research & Development - Railway Safety